Turmeric rhizome growth and higher yield

Turmeric Rhizome Growth and Higher Yield

To get a good turmeric yield and excellent growth of the rhizomes, it is very important to provide proper nutrition to the crop at different stages. The period after 120 days of planting is the main stage for rhizome swelling and growth. The fertilizer management done during this time has a direct impact on the crop's yield and quality.

Below is detailed information on this fertilizer management and drenching schedule for turmeric/rhizome crops.

Detailed fertilizer and drenching management for turmeric/rhizome crops

1. 120 days after planting (rhizome strengthening stage)

Purpose: To strengthen the rhizomes and ensure firm root anchorage.

Quantity and fertilizer: Fosid - 3 kg + Humol Jelly - 1 kg (per acre).

Method of application: Mix both components thoroughly in 200 liters of water and apply through drip irrigation.

2. 130 days after planting (micronutrient supply)

Purpose: To overcome nutrient deficiency in the crop and keep the leaves green.

Quantity and fertilizer: Ferrostar - 1 kg (per acre).

Method of application: Apply to the crop through drip irrigation.

3. 150 days after planting (phase of vigorous growth)

Objective: Ensure that the crop continues to grow and the tubers develop strongly.

Dosage and fertilizer: Release 9 - 3 kg + Calnet - 10 kg (per acre).

Method of application: Prepare the solution in 200 liters of water and release it through drip irrigation.

4. 165 days after planting (nutrient drenching)

Objective: To provide all the essential macro and secondary nutrients required by the tubers.

Dosage and fertilizer: 00:42:47 + FE - 2.5 kg + Humol Gold - 500 grams (per acre).

Method of application: Mix in 200 liters of water and apply through drip irrigation.

5. 180 days after planting (increasing tuber size - part 1)

Objective: To start increasing the size and weight of the tubers.

Dosage and fertilizer: K Surge - 200 grams + Sizegen - 1 liter (per acre).

Method of application: Prepare the solution in 200 liters of water and apply through drip irrigation.

6. 210 days after planting (increasing tuber size - part 2)

Purpose: To properly swell the tuber.

Dosage and fertilizer: 00:09:46 - 2.5 kg (per acre).

Method of use: Mix in 200 liters of water and apply via drip irrigation.

7. 240 days after planting (tuber size and protection)

Purpose: To fully swell the tuber and protect it from pests and diseases.

Dosage and fertilizer: 00:00:23 - 10 kg + Chloro - 1 liter (per acre).

Method of use: Mix together in 200 liters of water and apply via drip irrigation.

8. Final fertilization (last stage)

Purpose: To give the tuber full size, shine, and weight before harvest.

Dosage and fertilizer: K Surge - 200 grams + Sizegaen - 1 liter (per acre).

How to use: Mix in 200 liters of water and apply through drip irrigation.

Important instructions for farmers

Water management: Before and after giving fertilizers through drip, the soil should be moist (damp condition).

Preparing the solution: Make sure the fertilizers are completely dissolved in water so that the drip laterals or drippers do not get blocked.

Expert guidance: If you notice any other problem, pest, or disease in the crop, you can get direct advice by WhatsApp at 7507775355.